PLANT CONSTRUCTION CONTRACT

添加時間:2017-11-28 11:19:31
瀏覽次數(shù): 0
  article 1-definitions
  'the owner' shall mean .
  'the contractor' shall mean .
  'the plant' shall mean all or any part of the machinery, equipment andmaterials forming the permanent installation as specified in appendix.
  'the site' shall mean all the land where the plant is to be constructed in accordance with this contract.
  'the works' shall mean the works to be done by the contractor under this contract.
  'the contract price' shall mean the total sum payable to the contractor by the owner for the works.
  article 2-contractor''s responsibilities
  1. the contractor shall design, engineer, and construct the plant at the site.
  2. the contractor shall provide all equipment, materials, tools, facilities,labour and services necessary for the successful construction of the plant except those items and facilities to be supplied by the owner under article.
  3. the contractor shall perform the works in accordance with the schedule in appendix.
  4. the contractor shall provide the owner''s personnel with training of peration and maintenance of the plant in accordance with appendix.
  5. the contractor shall supply the owner with the spare parts specified in appendix.
  6. the contractor shall supply the owner with the maintenance equipment specified in appendix.
  article 3-owner''s responsibilities
  1. the owner shall make available the site and grant the contractor free and uninterrupted access thereto throughout the duration of this contract.
  2. the owner shall provide those items and facilities specified in appendix at the time therein established.
  3. the owner will obtain from the relevant authorities those licenses and permits necessary to construct and operate the plant on the site including work permit for the contractor''s employees.
  4. the owner shall pay the contractor for the works performed the contract price set out in article.
  article 4-contract price
  1. within days after the effective date of this contract, the owner shall pay the contractor as full and complete compensation for accomplishing the works and assuming all obligations under this contract the contract price in the amount of .
  2. the contract price is not subject to escalation, and the cost of executing he works shall be the risk of the contractor who shall be deemed to have btained all information and taken into account all circumstances which may affect the cost in agreeing the contract price.
  article 5-drawings
  1. the contractor shall submit to the owner for approval and review within he time specified in appendix _____ such drawings as may be required for construction of the plant under this contract. within one month after receiving such drawings the owner shall review and approve or disapprove the drawing.
  2. the contractor shall be responsible for any defects, errors or omissions in the above drawings unless such defects, errors or omissions are caused by inaccurate information furnished in writing to the contractor by the owner.
  3. all drawings and technical documentation delivered by the owner or the contractor to the other party shall be treated as confidential by the receiving party unless agreed otherwise, and shall not be used by that party for purposes other than those connected with this contract
  article 6-inspection
  1. the contractor shall perform all inspection and testing of the plant required by law and normal engineering practice.
  2. the owner shall be entitled at all reasonable times and at its own cost to inspect, examine and test the materials and workmanship of the plant under construction. such inspection, examination or testing if made shall not release the contractor from any obligation under the contract.
  3. the completed plant shall be inspected, examined and tested by the owner,and the contractor shall give the owner reasonable notice in writing of the date on which the plant will be ready for testing.
  4. the contractor shall provide such assistance, labour, materials, electricity,fuels, apparatus, stores and instruments as may be required and as maybe reasonably demanded to carry out such tests by the owner properly and efficiently.
  5. when the plant shall have passed the above tests, the owner shall furnish the contractor with a certificate in writing to that effect. no plant shall be delivered until any faults discovered during inspection are satisfactorily rectified.
  article 7-inspection
  1. the contractor shall provide at the site to the reasonable satisfaction of the owner all materials, labour, equipment, services and facilities that may be necessary for the proper execution and completion of the works.
  2. without prejudice to the generality of the above, the contractor shall provide, as may be necessary, the following:
  a. construction equipment.
  b. means of transport within the site including temporary roadways.
  c. fencing, lighting and guarding and all other materials and services necessary for the safety and security of persons and property.
  d. temporary stores, offices and other buildings or structures for materials and persons engaged in the words, including persons employed by the owner.
  e. telephones, fire-fighting equipment and first-aid equipment until the whole works have been taken over.
  f. sanitary and canteen facilities for the use of persons engaged in the works.
  3. the contractor shall observe all safety and other regulations imposed on the site by local laws.
  4. the contractor shall at all times keep the owner''s property and the adjoining premises, driveways and streets free of construction materials and rubbish caused by the works, and at the completion of the works shall remove all remaining materials from and about the premises and shall leave the site and plant safe, clean and ready for use.
  article 8-inspection
  1. the contractor will supply at his own cost food, transprot and all necessary facilities for all his own personnel.
  2. on signing the contract, the contractor shall appoint a project manager who will represent the contractor at all times be present at the site during working hours. all communications issued by the owner to the project manager shall be binding as if given to the contractor.
  3. the owner may request the removal and replacement of any person employed by the contractor on the site if such person is in the owner''s opinion guilty of misconduct, incompetence or negligence.
  article 9-inspection
  1. the contractor shall be responsible for all losses of or damage to the plant before final acceptance, and shall make good al such loss or damage at the cost of the contractor and to the reasonable satisfaction of the owner provided, however, in the case of loss or damage to the plant arising from or occasioned by causes for which the contractor is mot responsible under the contract, the same shall be made good by the contractor but at the cost of the owner, if the owner so directs.
  2. the contractor shall indemnify the owner in respect of all damage and in jury occurring before the issue of the final acceptance certificate to any property and person and against al l actions, suits, claims, demands, charges and expenses arising in connection therewith which shall be occasio ned by the negligence of the contractor or any of his sub-contractors or by defective design, materials or workmanship but not otherwise.
  3. in the event of any claim being made or actions brought against the owner arising out of any matter in respect of which the contractor is or may be liable under this article, the owner shall promptly notify the contractor in writing thereof and the contractor shall at his own expense take over and conduct in the name of the owner all negotiations for the settlement of the same and any litigation that may arise therefrom. the owner shall at the request of the contractor afford all such information and assistance as the contractor may reasonably require for the purpose of dealing with any such claim or action.
  article 10-inspection
  1. without limiting the contractor''s liabilities the contractor will at his own expense take out the following insurance:
  a. transportation insurance on the machine and equipment from its deliveryex works to arrival at the site.
  b. workers compensation insurance for all contractor''s and subcontractor''s employees engaged or similar statutory social insurance in accordance with the applicable laws and regulations.
  c. product liability insurance against damage to property or injury to persons until the end of the maintenance period in the sum not less that (amount) us dollars per occurrence.
  d. comprehensive automobile liability insurance in respect of all vehicles used by the contractor or his sub-contractor in connection with his contract.
  2. the aforesaid policies of insurance will be taken out in the names of the contractor and its sub-contractors, the owner, their engineer, consultant and employees and agents as the joint insured and the policies shall contain a waiver of insurer''s rights of subrogation against the owner, its engineer, consultant and employees and agents.
  3. the contractor shall maintain the aforesaid policies in full force and effect until the discharge of his obligations under this contract, and the owner shall have the right to demand from time to time copies of the policies, endorsements and renewals and receipts for payment of insurance premiums. if the contractor fails to maintain any of these policies in full force and effect, the owner shall have the right to rake out such policies and pay all relative premiums on behalf of the contractor and to deduct the relevant costs from and sums owing to the contractor.
  article 11-inspection
  1. on completion of all construction and erection work of the plant, the contractor shall inform the owner and shall carry out mechanical erection completion tests specified in appendix  to the satisfaction of the owner.
  2. on satisfactory completion of such tests the owner will issue a certificate of completion of erection of the plant. no feedstock shall be fed into the plant until a certificate of completion of erection has been issued.
  3. in the event of minor deficiencies in the construction and erection work which do not prevent erection completion and/or in the event of defects revealed by the tests which do not prevent the start-up of the plant, the owner shall issue a certificate of completion of erection and the contractor shall be obliged to rectify the deficiencies as quickly as possible thereafter.
  article 12-inspection
  1. following the issue of the certificates of completion of erection the contractor shall give the owner days notice of the date when he will be ready to carry out performance tests of the plant.
  2. the owner shall provide the feedstock and other facilities required in appendix to enable the tests to commence on time and the contractor shall begin the performance tests at the time so notified.
  3. the performance tests will be carried out in acceptance with the provisions of appendix  and on their successful completion, the owner shall issue a final acceptance certificate stating that the plant has been taken over by the owner as from the date thereof.
  4. if the plant fails to pass its performance test, then the contractor,after making such adjustments as he considers necessary, shall repeat such tests in the presence of the owner at a time to be agreed upon under the same terms and conditions as the original tests.
  5. the plant shall not be commercially operated before the issue of the final acceptance certificate. notwithstanding the failure of the plant to pass its performance tests, the owner may at his discretion issue a final acceptance certificate subject to the contractor remedying the plant defects as soon as possible.
  article 13-inspection
  1. in the event of any repeat of a performance test failing for reasons imputable to the contractor, and there being no mutual agreement to continue retesting, the results of the final test will be measured and the contractor will be liable to pay to the owner liquidated damages on the scale set out in appendix up to a maximum of % of the contract price.
  2. if the contractor is unable for reasons within his control to obtain a final acceptance certificate for the whole plant by months from the effective date of this contract, he shall be liable to pay to the owner for each month''s delay liquidated damages of% of the contract price up to a maximum of% of the contract price in accordance with appendix.
  3. the contractor shall establish, in favour of the owner, a guarantee for% of the contract price in the form set out in appendix in support of his obligations under this article.
  article 14-inspection
  1. the contractor warrants, for a period of  months from the date of issue of the final acceptance certificate or months from the effective date of this contract whichever is the earlier, the supplied plant against faulty design, material and workmanship.
  2. the owner shall inform the contractor in writing of all claims arising under this provision within days of the detection of fault, if the contractor''s representative is on site or withindays if not, to the contractor''s head office by telex r recorded air mail delivery with supporting data. the contractor shall have the option to replace or repair all parts proved deficient. for this purpose the contractor shall have the option to replace or repair all parts proved deficient. for this purpose the contractor shall have an access to the site to inspect the faulty parts at any time and to enable him to comply with the terms of this guarantee. should the contractor fail to carry out agreed remedial work within any period of time reasonable in the particular circumstance, the owner shall have the right to do this work at the contractor''s expense.
  3. this warranty is given subject to the owner storing, operating and maintaining the plant in accordance with the contractor''s instructions and specified operating parameters and may be nullified in the event of the owner attempting rectification work without the contractor''s agreement.
  4. this warranty does not include items which fail due to natural wear and tear, or consumables or similar items whose natural life is  months or less.
  5. if pursuant to the above warranty the contractor repairs or replaces any equipment, materials or workmanship, the provisions of this article shall them apply to said repaired or replaced equipment, materials or workmanship for a period of one year from the date such repairs or replacements are completed.
  article 15-patent rights and royalties
  1. the contractor shall fully indemnify the owner against all actions,claims, demands, costs, charges and expenses arising from or incurred by reason of any infringement of patents, design or copyright of third parties by the use of the plant supplied by the contractor.
  2. the contractor shall also be responsible for the payment to third parties of all fees, royalties and other charges, if and, that may be payable under the terms of any license or permission in respect of any design of the works provided by the contractor, the manufactured and supply of the plant and any work done or method employed in the construction of the works.however, the owner shall be responsible for the payment to third parties of all fees, royalties and other charges, if any, that may be payable under the terms of any license or permission in respect of the operation or use of the plant or any part thereof.
  article 16-suspension
  1. the owner shall have the right to instruct the contractor to suspend any part or the whole of the works at any time upon giving written notice to the contractor provided that any period of suspension exceeding days shall be treated as termination under article.
  2. if the owner fails to make any payment to the contractor under this contract within days of the due date, or if the contractor is otherwise interrupted or delayed in the performance of the works due to the owner''s contractual default, the contractor shall be entitled to suspend performance of this contract.
  3. in the event of suspension of the works in accordance with this article the contractor shall be entitled to receive such reasonable additional payment as may be necessary to compensate for the additional costs arising out of such suspension, interruption or delay and such reasonable extension of time for performance of contract.
  article 17-termination
  1. in the event of suspension in accordance with article lasting for a period of more than  days either party shall have the right to give notice to the other party of the immediate termination of this contract.
  2. the owner may at any time by written order to the contractor order the contractor to cease further execution of the works, and the contractor shall upon receipt of a termination order, cease all further work on the site other than such work thereon as the engineer may instruct for the purpose of protecting, making safe or tidying up such parts of the works as may already have been executed or be in course of erection. the contractor shall, as soon as practicable after receipt of the termination order, also cease all such further work as is being done off the site in the performance of this contract.
  3. upon termination of this contract under this article and under article, the contractor shall be entitled to be paid:
  a. that part of the contract price which is proportionate to engineering and services carried out, and
  b. that part of the contract price which is proportionate to the plantcompleted but not delivered.
  article 18-force majeure
  1. no party to this contract shall be liable to the other party for any failure of or delay in performance of its obligations hereof nor be deemed to be in breach of this contract, if such failure or delay has arisen from'force majeure.'
  2. 'force majeure' means circumstances and conditions beyond the control of either parties, that would render it impossible for either the owner or the contractor to fulfill their obligations under this contract, or delay such fulfillment. any of the following matters are considered 'force majeure.'
  a. war, hostilities, act of foreign enemy, invasion, warlike opera-tions(whether war to be declared or not) or civil war;
  b. mutiny, civil commotion assuming the proportions of or amounting to a popular rising, military rising, insurrection, rebellion, revolution,military or usurped power, or any act of any person acting on behalf of or in connection with any organization with activities directed towards the overthrow by force of the government de jure or de facto, or to the influencing of it by terrorism or violence;
  c. earthquake, flood, fire or other natural physical disaster;
  d. denial of the use of all ports, airports, shipping services or other means of public transport;
  e. strike or lock out or other industrial concerted action by workers,affecting the fulfillment of contractor''s and subcontractors'' obligations;
  f. and other unforeseen circumstances beyond the control of the parties so affected rendering the fulfillment of their obligations impossible.
  3. if either party to this contract is prevented or delayed from or in performing any of his obligations under this contract by force majeure,then he may notify the other party of the circumstances constituting the force majeure and of the obligation performance of which is thereby delayed or prevented and the party giving the notice shall thereupon be excused from the performance or punctual performance, as the case may be, of such obligation for so long as the circumstances of prevention or delay may continue.
  4. if by virtue of the preceding sub-clause dither party shall be excused from the performance or punctual performance of any obligation for a continuous period of  months, then either party may at any time thereafter terminate this contract by giving a written notice to the other party.
  article 19-assignment and sub-contractors
  1. the contractor shall have the right to sub-contract this contract or any part thereof in accordance with his usual practice without relieving the contractor of the obligations of performing this contract.
  2. neither party shall without the previous consent in writing of the other party assign or any part thereof to any third party, except in the case of a company amalgamation or reconstruction, provided that such consent shall not be unreasonably withheld.
  article 21-effective date of the contract
  1. the effective date of this contract shall be the date after its execution when all the necessary approvals of the respective authorities have been obtained by the owner.
  2. if the contract does not become effective within days from the date of execution, it will be deemed void unless otherwise agreed between the parties.
  article 22-law and regulations
  1. the contractor shall in all matters relating to the performance of this contract conform with all applicable laws, regulations and orders of central or local authorities.
  2. the construction, validity and performance of this contract shall be governed in all respects in accordance with the laws
  article 23-entire contract
  1. this contract constitutes the entire agreement between the parties and supersedes all prior negotiations, representations or agreements whethea oral or in writing relative to the subject matter of this contract.
  2. this contract shall be altered or supplemented only by mutual consent in writing between the owner and the contractor.
  article 24-language of the contract
    this contract was drafted in english language and the english text of this contract shall be valid and binding upon the parties hereto.
  article 25-notices
  1. every notice, consent, instruction, order or decision given under this contract shall be given or m ade in writing and either personally served on an officer of the party to whom it is given or airmailed post-prepaid or sent by telegram, telex or cable subsequently confirmed by letter, addressed as follows:
  to: the owner
  (address)
  to: the contractor
  (address)
  2. notices, consents, requests and other documents shall be deemed delivered or given, if mailed to an overseas destination, on the __ th day after the date of mailing and, if mailed to a domestic destination, the __ day after the date of mailing. notices, consents or requests sent by telegram,telex or cable shall be deemed delivered or given on the day they are despatched.
  3. any notice, consent, instruction, or decision given under this article shall be signed on behalf of either party by any duly authorised representative of that party. either of the parties may change his address for receipt of notices, instructions or decisions and other documents at any time by giving notice thereof in writing to the other party.
 
 
 
主站蜘蛛池模板: 亚洲第一色图_免费的日批视频_超碰97在线播放_激情综合丁香五月_蜜臀av入口_亚洲欧美婷婷五月色综合_www高清_日韩在线免费 | 国产精品久久久久国产精品三级_免费观看老乱熟视频_日韩精品在线视频观看_天海翼精品一区二区三区_亚洲一线视频_四虎伊人_国内精品小视频_人妻出轨和黑人疯狂做国产人 国产精品国产三级国产av′_www国产精品_www.精品视频_奇米在线7777在线精品_性生交裸片免费看_91爱观看在线_夜夜草影院_中文字幕亚洲日本 | 日韩视频三区_色天天爱天天狠天天透_99精品成人_在线观看欧美一级_四虎影院观看视频在线观看_91伦理在线_亚洲AV无码久久_91最新 | JAPANESEXXXX日本熟妇伦视频_色哟哟网站在线观看_一区二区三区在线免费看_久久中文字幕人妻丝袜_jizzjizz國产免费a片_国产一区一一区高清不卡_91桃色在线看_国产91视频网 | 好看的一级毛片_91视频进入_爱爱视频免费_xxx国产老太婆视频_久久精品午夜_日本在线不卡观看_最新高清无码专区在线视频_а天堂最新版中文在线 | 国产精品久久影院_免费A级毛片黄A片高清在线播放_亚洲大片在线_久久99热婷婷精品一区_国产精品亚洲swag_91久一久精品日日躁夜夜躁国产_午夜dj视频免费观看www_欧美区精品系列在线观看不卡 | 久久99久久99精品中文字幕_一级毛片免费版_a国产免费_玖玖视频免费_日日激情综合久久一区_91久久国产精品视频_爱福利视频网_天天碰天天摸天天操 | 草逼逼视频_91欧美一区二区三区综合在线_美女床上运动_日韩一区二区三区高清_老中医吮她的花蒂和奶水视频播放_视频一区二区三区在线播放_99国产精品国产精品九九_一区二区精 | 97热久久_91视频合集_在线免费亚洲视频_日本高清色www在线安全_久久久网站av_999精品在线观看视频_91精品国产综合久久香蕉922_国产第一页在线观看 | av免费在线一区二区三区_一本毛片_av伊人网_丁香五精品蜜臀久久久久99网站_人妻少妇乱子伦精品_91日韩中文字幕_欧美疯狂做受BBBBBB_波多野结衣一区在线观看 | 久热这里只有精品12_麻豆国产在线视频_国产日韩欧美精品一区_成年片色大黄全免费网无需安装_久久伊人少妇熟女大香线蕉_在线不卡中文字幕一区_欧美大胆丰满熟妇XXBB_国产精品久久中文 | 91久久久久久亚洲精品禁果_午夜福利123_国产一二区免费视频_国产99久久久久久免费看农村_国产成人精品国内自产拍_91在线看看_日韩免费观看视频_熟妇人妻AV无码一区二区三区 | 欧美三级黄色大片_亚洲韩国一区二区_亚洲精品岛国片在线观看_国外一级黄色片_91看片淫黄大片91桃色_1314酒色网_国产夫妻自拍小视频_久久精品国产亚洲aa级女大片 | 亚洲中文字幕无码永久免弗_亚洲熟妇丰满XXXXX_日韩视频专区_免费观看黄色大片_男女无套免费视频网站_欧洲精品一区二区三区在线观看_www.91视频69xx.com_色七七桃花影院 | 久久精品国语对话_亚洲天天摸日日摸天天欢_日韩AV无码一区二区三区不卡_日本污漫_日本在线理论片手机观看_久久精品国产免费_国产freesexvideos中国麻豆_亚洲欧洲精品无码av | 亚洲AV午夜福利精品一区二区_亚洲精品一区二区国产精华液_国产91在_亚洲精品在线观看一区二区_99久久99热这里只有精品_91久久久久久久久久久久久_哪里可以看免费的av_日韩有码第一页 | 99久久精品国产免费看不卡_好紧好湿太硬了我太爽了_欧美激情一区二区三区视频_宅男天堂_精品三级久久久_gogogo高清在线观看视频中文_免费国产白丝喷水娇喘视频site:_青青草视频黄 | 麻豆TV入口在线看_国产一区在线导航_青草视频在线免费观看_性色av无码专区一ⅴa亚洲_国产精品com_国产a三级久久精品_久久一区国产_精品国产日韩欧美一区二区 | 日韩精品不卡一区二区_久久久久久久久久久免费_久久91亚洲精品久久91综合_免费高清国产_久久免费福利_日本一区二区三区免费_无码人妻丰满熟妇啪啪7774_亚洲一区二区三区香蕉 高清不卡免费视频_猛烈顶弄H禁欲老师H春潮视频_国产老肥熟精品大全_亚洲欧美成人a毛片_亚洲精品在_第一区免费在线观看_免费国产自久久久久三四区久久_亚洲男人的天堂网 | 激情信封_第一色综合_国产首页视频一区二区_99精品久久久久久久久久综合_国产午夜性春猛交xxxx公交车_国产成人在线网站_91成人免费无码成人影院日韩_性av网址 | 91久久精品国产一区二区三区_一本大的之伊人_国产免费观看视频_一级片aaa_国产国在线线免费费_久久精品国产亚洲αv忘忧草_WWW国产精品内射熟女_2012中文字幕在线视频 | 人妻暴雨中被强制侵犯_久久久久久久无码高潮_欧美xxxx做受欧美88bbw_国产男女猛视频在线观看_啦啦啦免费视频播放_99视频福利_99re这里只有精品在线_老司机成人精品视频 | a级高清免费毛片av在线_日韩乱视频_久久九九高潮毛片免费全部播放_少妇BBWBBW高潮_黑色东京在线观看_亚洲欧洲日产国码无码AV一_韩国日本美国免费毛片_国产精品69久久久久水密桃 | 俄罗斯美女肛交内射WWWC〇M_国产成人亚洲综合网站_国产成人无码AV在线播放DVD_无码视频在线观看_天天操夜夜草_亚洲综合一区自偷自拍_国产在线观看成人_在线免费av网址 | 亚洲三区在线视频_亚洲色图片区_久久久999精品视频_日韩一级黄色影片_黄色片免费在线观看_成人a视频片在线观看免费_青青青伊人_狠狠一区 | 午夜精品影院_中文JAPANESE在线播放_精品三级_林深见鹿40集高清免费观看_国产一级αv片免费观看_青草久久国产_超碰个人97_广西美女色炮150p图 | 免费www_他一边曰一边吃我奶小说免看_日产精品卡1卡2免费_国产精品呻吟久久av凹凸_免费网站在线观看黄色_亚洲欧美日韩在线一区二区_白袜奴gay网站_欧美黄网站在线观看 午夜精品中文字幕_贪婪欲望之岛在线播放_爱情岛亚洲AV永久入口首页_免费看黄视频在线_亚洲国产A∨无码中文777_中文字字幕码一二区_国产精品亚洲а∨天堂网_国产明星裸体无码XXXX视频 | 麻豆freexxxx性91精品_又黄又湿啪啪响18禁_午夜一级精品_免费A级毛片出奶水_WWW国产内插视频_最近中文字幕视频高清_日韩欧美国产区_亚洲欧美国产国产一区二区 | 法国《性迷宫》在线观看_亚洲色欲天天天堂色欲网_av永久免费在线观看_JIZZ国产精品_国产精品视频三区_免费无码毛片一区二三区_风间由美久久久_黄色片av网站 | 又湿又紧又大又爽A视频_色八区人妻在线视频免费_玩弄丰满少妇XXXXX性多毛_美女av影视_午夜好爽好舒服免费视频_亚洲一区二区麻豆_97精品在线_日本免费小视频 | 好看的一级毛片_91视频进入_爱爱视频免费_xxx国产老太婆视频_久久精品午夜_日本在线不卡观看_最新高清无码专区在线视频_а天堂最新版中文在线 | 人妻免费久久久久久久了_办公丝袜av一区二区三区_2019日韩中文字幕mv_国产黄频免费无数次看_国产精品国产成人国产三级_动漫久久_午夜男女XX00视频福利_日韩高清在线不卡一区二区 | 久久久无码精品亚洲日韩啪啪网站_国产三级三级看三级_天堂一区人妻无码_国产成人久久精品_最近中文字幕2019视频1_思思久热_亚洲成AV人在线观看成年美女_日韩少妇内射免费播放18禁裸乳 | 一本到不卡_狠狠色丁香四月婷婷综合_色噜噜AV男人的天堂_99国产伦精品一区二区三区_99黄色网_久久久久九九九九九_亚洲精品乱码久久久久久久久久_亚洲精品久久久久午夜aⅴ | 国产精品色片_看一级片_在线超碰av_日日干夜夜操_日韩国产91_粉嫩虎白女在线观看中国女_久久综合色播_免费av影片 | 中国久久久_动漫AV网站免费观看_av大西瓜_久草久视频_国产精品男同志movies_精品国产免费一区二区三区五区_性猛交xxxx乱大交孕妇免费看_wwwxxx国产 | 日本aⅴ视频_亚洲中文字幕在线无码一区二区_免费xxx视频_久久综合免费视频_蜜桃人妻无码AV天堂三区_又粗又紧又湿又爽的免费视频_国内精品成人_亚洲网在线 | 亚洲视频aaa_日本19禁啪啪免费观看www_国产一区二区三区四区www._亚洲精品久久久久中文字幕欢迎你_亚洲精品50p_av无码午夜福利一区二区三区_亚洲第一免费播放区_91一区在线 | 久草香蕉在线_亚洲免费成人av_男人女人一边躁一边爽视频_日韩亚洲一区在线播放_欧美一区二区小视频_日本午夜片_欧美精品国产综合久久_国产黄色A一片免费看 | 国色天香2019中文字幕在线观看_亚洲AV无码传区国产乱码O_97在线免费公开视频_熟女无套高潮内谢吼叫_国产精品嫩草影院入口一二三_国产亚洲欧美日韩精品一区二区三区_乱色欧美激情亚洲欧美激情_四虎在线免费观看视频 | 国产成人无码精品午夜福利A_日本熟妇HD人妻_国产成年无码a∨片在线韩国_秋霞福利_午夜精品91_AA片子吇中文字处女_欧美夜噜噜免费观看_国产精品青青草原免费无码 |